Article content
City staff are hoping to minimize disruptions for transit riders during construction on the St-Laurent LRT station, which is anticipated to begin in the summer of 2028 and could shut down the tracks in both directions for several weeks.
THIS CONTENT IS RESERVED FOR SUBSCRIBERS ONLY
Subscribe now to read the latest news in your city and across Canada.
- Unlimited digital access to the Ottawa Citizen.
- Analysis on all things Ottawa by Bruce Deachman,David Pugliese, and others, award-winning newsletters and virtual events.
- Opportunity to engage with our commenting community.
- Ottawa Citizen ePaper.
- Ottawa Citizen App.
SUBSCRIBE TO UNLOCK MORE ARTICLES
Subscribe now to read the latest news in your city and across Canada.
- Exclusive articles from David Pugliese, Andrew Duffy, Bruce Deachman and others. Plus, food reviews and event listings in the weekly newsletter, Ottawa, Out of Office.
- Unlimited online access to Ottawa Citizen and 15 news sites with one account.
- Ottawa Citizen ePaper, an electronic replica of the print edition to view on any device, share and comment on.
- Daily puzzles, including the New York Times Crossword.
- Support local journalism.
REGISTER / SIGN IN TO UNLOCK MORE ARTICLES
Create an account or sign in to continue with your reading experience.
- Access articles from across Canada with one account.
- Share your thoughts and join the conversation in the comments.
- Enjoy additional articles per month.
- Get email updates from your favourite authors.
Register to unlock this article — it’s free
Create an account or sign in to continue with your reading experience.
- Access articles from across Canada with one account
- Share your thoughts and join the conversation in the comments
- Enjoy additional articles per month
- Get email updates from your favourite authors
Sign In or Create an Account
or
Article content
A report from the Stantec engineering firm, which was attached to a request for tenders posted by the City of Ottawa, outlined extensive rehabilitation work to mitigate the “serious risk” of deteriorating concrete in the station’s lower-level ceiling.
Article content
Article content
Article content
The estimated $7.9-million renewal project is expected to take 11 to 13 months, according to the report, and would require several stages of track closures at the busy O-Train LRT station to facilitate the work while also maintaining safety for the public and for maintenance workers.
Article content
By signing up you consent to receive the above newsletter from Postmedia Network Inc.
Article content
Carina Duclos, the city’s director of infrastructure services, sent a memo to the mayor and council on July 30 to respond to questions raised by councillors on the condition of the tunnel infrastructure, the renewal project timelines and the potential impacts to transit customers.
Article content
The Stantec report was “meant to inform the scope of the design work to be undertaken” and it highlighted “several possible staging options,” Duclos wrote.
Article content
Stantec proposed a staging sequence requiring single-track closures of nine to 10 weeks for each track, platform closures of four to five weeks per platform and full closure of both tracks for five to six weeks to facilitate the rehabilitation work.
Article content
“These will be refined and further assessed as part of this design work. Only when the detailed design is complete will city staff determine and recommend the most appropriate construction approach to council,” Duclos wrote. “This will prioritize an approach that minimizes disruptions to transit customers.”
Article content
Article content
The St-Laurent tunnel renewal project is part of the city’s ongoing lifecycle renewal program, which “proactively rehabilitates critical infrastructure to ensure it remains safe, reliable, and resilient for years to come,” Duclos said. The rehabilitation is expected to extend the structure’s service life by 15 years.
Article content
Article content
“I want to reassure members of council that St-Laurent Station remains safe for customers and staff. The station and tunnel infrastructure continue to be regularly inspected and monitored, and appropriate measures are in place to support the safe operation of O-Train Line 1.”
Article content
The station and tunnel structures are in “generally good condition,” though some components have been identified as being in “fair to poor condition” through the city’s regular inspection process. Those components have been “prioritized” for renewal, Duclos said, and updated information has been shared with the transit committee.
Article content
Duclos said the project was currently in the procurement stage to retain detailed design services and staff were following the normal process for infrastructure projects.