Vaughn Palmer: On new Fraser River tunnel, NDP hoping voters aren't paying attention

1 week ago 21
Preparatory work for the new tunnel underway beside the southern entrance to the aging George Massey TunnelPreparatory work for the new tunnel underway beside the southern entrance to the aging George Massey Tunnel. Photo by Ministry of Transportation and T /Government of B.C.

Article content

VICTORIA — Transportation Minister Mike Farnworth delivered a series of excuses this week to explain why the NDP plan to replace the Massey tunnel has gone more than 100 per cent over budget and fallen a full year behind schedule.

Vancouver Sun

THIS CONTENT IS RESERVED FOR SUBSCRIBERS ONLY

Subscribe now to read the latest news in your city and across Canada.

  • Unlimited online access to articles from across Canada with one account.
  • Get exclusive access to the Vancouver Sun ePaper, an electronic replica of the print edition that you can share, download and comment on.
  • Enjoy insights and behind-the-scenes analysis from our award-winning journalists.
  • Support local journalists and the next generation of journalists.
  • Daily puzzles including the New York Times Crossword.

SUBSCRIBE TO UNLOCK MORE ARTICLES

Subscribe now to read the latest news in your city and across Canada.

  • Unlimited online access to articles from across Canada with one account.
  • Get exclusive access to the Vancouver Sun ePaper, an electronic replica of the print edition that you can share, download and comment on.
  • Enjoy insights and behind-the-scenes analysis from our award-winning journalists.
  • Support local journalists and the next generation of journalists.
  • Daily puzzles including the New York Times Crossword.

REGISTER / SIGN IN TO UNLOCK MORE ARTICLES

Create an account or sign in to continue with your reading experience.

  • Access articles from across Canada with one account.
  • Share your thoughts and join the conversation in the comments.
  • Enjoy additional articles per month.
  • Get email updates from your favourite authors.

THIS ARTICLE IS FREE TO READ REGISTER TO UNLOCK.

Create an account or sign in to continue with your reading experience.

  • Access articles from across Canada with one account
  • Share your thoughts and join the conversation in the comments
  • Enjoy additional articles per month
  • Get email updates from your favourite authors

Sign In or Create an Account

or

Article content

At a news conference on Monday, he blamed “inflation, project scope, today’s market conditions and the realities of delivering a project of this size and complexity.”

Article content

Article content

Article content

But as the week unfolded, Farnworth had trouble reconciling the contradictions in the NDP message box.

Article content

Article content

Inflation?

Article content

In 2021, the New Democrats issued a supposedly precise estimate of $4.15 billion as the cost of delivering the finished eight-lane tunnel by mid 2030. Today, they say it will cost $8.5 billion and the crossing won’t be open to traffic until the fall of 2031.

Article content

Inflation in Canada has increased prices by 20 per cent between the two estimates, enough to account for a $1 billion increase in the cost of construction, not the $4.35 billion admitted by the New Democrats.

Article content

Project scope? Elsewhere this week, Farnworth said the New Democrats had made no significant changes in the project scope to account for any increased costs.

Article content

“In a nutshell, the project is staying exactly the same in terms of the scope. There’s been no changes in the scope of the project,” he acknowledged Tuesday.

Article content

Then again one politician’s “nutshell” could be another’s case of financial overreach.

Article content

As for “today’s market conditions,” Farnworth did indeed blame them for the overrun on the Massey replacement. Yet he also cited “market soundings” to justify the decision to dump the lead contractor on the project and retender it in several pieces.

Article content

Article content

“We will get very competitive bids,” claimed Farnworth, apparently forgetting that he’d cited those same market conditions to explain the overrun with the initial contractor.

Article content

B.C. Minister of Transport Mike Farnworth stands in the Great Northern Way station of the new Broadway Subway line in Vancouver on June, 2, 2025. B.C. Minister of Transport Mike Farnworth stands in the Great Northern Way station of the new Broadway Subway line in Vancouver on June, 2, 2025. Photo by RICHARD LAM /PNG

Article content

Article content

He also fudged a major delay in the project timeline, claiming it had shifted only “modestly” and “slightly,” yet “remains broadly in line with what we initially anticipated.”

Article content

Not so.

Article content

The Aug. 18, 2021, technical briefing on the project said that environmental review would be completed by the end of 2025, major construction would start at the beginning of 2026 and the crossing would be open in mid-2030.

Article content

The revised timeline for each of those exercises is now advanced by one full year, turning the four-year schedule into five years, a 25 per cent overrun.

Article content

Farnworth calls that a “slight” change. He shouldn’t be so modest.

Article content

Waxing philosophical, the minister tried to rationalize the difference between the 2021 budget and this week’s dramatic revision.

Article content

“As you progress along what the design of the project is, you are able to refine your costs more accurately, and that’s where we are today,” said Farnworth.

*** Disclaimer: This Article is auto-aggregated by a Rss Api Program and has not been created or edited by Bdtype.

(Note: This is an unedited and auto-generated story from Syndicated News Rss Api. News.bdtype.com Staff may not have modified or edited the content body.

Please visit the Source Website that deserves the credit and responsibility for creating this content.)

Watch Live | Source Article